Timetable
This is the project's timetable:
- Identification and Concept Review - November 2001
- Presentation, Funding, Government accord - October 2002
- Discussions with World Bank and GTZ project staff - Spring 2003
- Revised Concept Note - June 2003
- Project area identification, Logistics setup, Local hiring - May 2004
- Data collection, Oum Lelli and Sawana wetlands - June-September 2004
- Satellite photography of project area - August-September 2004
- Data collection, Chlim wetland - Winter 2005
- Training and capacity building - Winter 2005
- Participatory processes, locally and nationwide - Winter-Spring 2005
- Consolidation, comparison, integration, process-building - Spring 2005
The timetable is continually revised to reflect the current situation with regard to implementation.